News
Current  Archive  
WP422-kickoff
Tuesday, June 15, 2010 (98 reads)


IMSK has now started the work packages for the sub-system design. During June all work packages for sub-system design will have a kickoff to start the work and WP422 Checkpoints was the first one. The kickoff was held the 1st-2nd of June at Saab facilities in Gothenburg.

During the kickoff all contributors presented their plans for the work within the work package. We went through the Description of Work and discussed the objectives, tasks and deliverables. The time schedule including the plan for progress meetings were presented and agreed. The workload within the tasks and the different task leaders were set.

The coming kickoffs for WP421-7 will take place in Überlingen, Florence, Paris and Luton during the coming weeks.



Read More
Project Management Review
Thursday, April 29, 2010 (184 reads)


 The IMSK project had the first Project Management Review Monday the 26th of April 2009.


The Project Officer Mr Clément Williamson together with two experienced expert reviewers Mr Konstantinos Leivaditis Retired Police Major General Former Director of the Hellenic Police Informatics Division and Mr José Antonio Diaz Project Leader from ISDEFE, the Spanish Defence Agency was presented the work performed in all Work Packages started during the first reporting period of the project.

Comments and requests to make documents connected to investigations of standards and legal restrictions open was given to the project. Any documents that is decided to be made public will be published at this web site.

The IMSK-project was represented by the Core-team and the French Ministry of Interior

 



Read More
WP410 Technical Workshop
Friday, March 12, 2010 (219 reads)


A Technical workshop within Work Package 410, Overall System Design, was held the 9th-10th of March in Amsterdam. Representatives from all core-team members worked together to find common views of the overall architecture, information flow and infrastructure.

 

WP410 shall be finalised in the end of June 2010 and in connection to that the sub-system design starts.



Read More
CDR311-316 - Technical Analysis
Thursday, February 18, 2010 (241 reads)


The second planned Critical Design Review (CDR) in the IMSK-project was held at Selex Communications premises in Florence. The goal of the CDR is to review al deliverables in the first part of the technical analysis work packages.

The CDR is connected to Mile Stone 3 in the project, planned to be passed in the end of February 2010.

 

 



Read More
Mile Stone review in Gothenburg
Monday, November 23, 2009 (414 reads)


Last week the IMSK project had the first Mile Stone review of the project. The Top Level System Requirements derived from the End-users needs was reviewed and when approved the first Mile Stone will be passed.

 



Read More

 Summary

 
The continuously evolving threat of unpredictable terrorist activity demands the innovative application of existing and developing technology for the protection of the EU’s citizens. The Integrated Mobile Security Kit (IMSK) project will combine technologies for area surveillance; checkpoint control; CBRNE detection and support for VIP protection into a mobile system for rapid deployment at venues and sites (hotels, sport/festival arenas, etc) which temporarily need enhanced security.


To succeed, the project will employ legacy and novel sensor technologies, design a system (IMSK) that will integrate sensor information to provide a common operational picture where information is fused into intelligence, perform a field demonstration to validate the concept, adapt the system to local security forces and finally disseminate the results after accreditation by end-users. The development of IMSK will be heavily founded on advice derived from operational security professionals.


The major key innovation introduced by IMSK is that all technological issues involved in the design implementation and integration of a complete technological information platform will be addressed.